Iraq: Mosul Dam Engineers Warn It Could Fail at Any Time, Killing 1 Million People

March 3rd, 2016

Via: Guardian:

Iraqi engineers involved in building the Mosul dam 30 years ago have warned that the risk of its imminent collapse and the consequent death toll could be even worse than reported.

They pointed out that pressure on the dam’s compromised structure was building up rapidly as winter snows melted and more water flowed into the reservoir, bringing it up to its maximum capacity, while the sluice gates normally used to relieve that pressure were jammed shut.

The Iraqi engineers also said the failure to replace machinery or assemble a full workforce more than a year after Islamic State temporarily held the dam means that the chasms in the porous rock under the dam were getting bigger and more dangerous every day.

On Wednesday, the Iraqi government announced it had signed a €273m (£210m) contract with an Italian contractor to reinforce and maintain the Mosul dam for 18 months, following talks in New York between the Italian foreign minister, Paolo Gentiloni, and US and Iraqi officials. Italy has said it plans to send 450 troops to protect the dam site, but it is unclear how long it will take to replace damaged machinery and reassemble the required workforce.

Leave a Reply

You must be logged in to post a comment.